
[Jan-2025] APICS CPIM Exam Practice Test Questions - Lead2PassExam
Updated Certification Exam CPIM Dumps - Practice Test Questions
The CPIM certification exam is divided into two parts: CPIM Part 1 and CPIM Part 2. CPIM Part 1 covers the basics of supply chain management, including topics such as demand management, material requirements planning, and capacity planning. CPIM Part 2 focuses on more advanced topics such as strategic management of resources, sales and operations planning, and execution and control of operations. Certified in Production and Inventory Management certification exam is computer-based and consists of multiple-choice questions. Candidates must pass both CPIM Part 1 and Part 2 within three years to earn the CPIM certification.
NEW QUESTION # 243
The message in which the planner must tell the MRP software of all actions taken that will influence the MRP records called
- A. Exception messages
- B. None of the above
- C. Bottom-up re-planning
- D. Transaction messages
Answer: D
NEW QUESTION # 244
A planned decision by the organization to select one supplier for an item when several sources are available is called:
- A. unique sourcing
- B. singular sourcing
- C. single sourcing
- D. sole sourcing
Answer: C
NEW QUESTION # 245
Which of the following strategic option/s is/ are used as success criteria for a corporate strategy?
- A. Feasibility (can it be made to work?)
- B. Suitability (would it work?)
- C. Acceptability (will they work it?)
- D. All of these
Answer: D
NEW QUESTION # 246
What consist of a series of operations required to make the item?
- A. All of the above
- B. procedures
- C. routing
- D. builds
Answer: C
NEW QUESTION # 247
A convenient way to think about bills of material is through:
- A. All of the above
- B. Dependent demand
- C. Product Tree
- D. Inventory record
Answer: C
NEW QUESTION # 248
Owner's equity is:
- A. Difference between revenues and expenses
- B. Difference between assets and revenues
- C. Difference between assets and liabilities
- D. Difference between expenses and liabilities
Answer: C
NEW QUESTION # 249
Production management is concerned with:
- A. The quantities of each production group that must be produced in each period \
- B. The resources of equipment, labor, and material needed in each period, and the availability of the resources needed
- C. The desired inventory levels
- D. All of these
Answer: D
NEW QUESTION # 250
The purchase cost of the stock-keeping units or the cost of manufacturing the item is called:
- A. Elementary cost
- B. Key cost
- C. Unit cost
- D. Economic cost
Answer: C
NEW QUESTION # 251
A process costs $200 to set up. The run time is 5 minutes per piece and the run cost is $30 per hour. Determine total cost and unit cost for a lot of 500.
- A. Total Cost: $1455.00 & Unit cost: $2.90
- B. Total Cost: $1400.00 & Unit cost: $2.80
- C. Total Cost: $1440.00 & Unit cost: $2.60
- D. Total Cost: $1450.00 & Unit cost: $2.90
Answer: D
NEW QUESTION # 252
A control chart for averages and ranges tracks which critical characteristics of a frequency distribution?
- A. control and tolerance
- B. shape and spread
- C. center and spread
- D. specification limit and center
Answer: C
NEW QUESTION # 253
The plan must be checked against available capacity when needed to make the components is called the process of
- A. Capacity Requirement planning
- B. Production Activity control (PAC)
- C. Material Requirements planning (MRP)
- D. A & C
Answer: A
NEW QUESTION # 254
Which of the following is NOT the method accounting use to cost inventory?
- A. First in first out
- B. Analysis cost
- C. Last in first out
- D. Average cost
Answer: B
NEW QUESTION # 255
Each of the following actions would reduce safety stock levels EXCEPT:
- A. reduce forecast error
- B. adopt a make-to-order strategy
- C. increase lead times
- D. reduce the customer service target
Answer: C
NEW QUESTION # 256
MRP and CRP should form part of a/an?
- A. Closed-loop system
- B. Open system
- C. Workable plan that meets the priority objectives
- D. Balanced system
Answer: A
NEW QUESTION # 257
The step for preparing MPS is/are:
- A. Check the preliminary MPS against available capacity
- B. Resolve differences between the preliminary MPS and capacity availability
- C. Develop a preliminary MPS
- D. All of these
Answer: D
NEW QUESTION # 258
ISO does not provide the documentation but specifies generic requirements for management that are typically grouped into which of the following levels:
- A. plan, procedures, performance and proof
- B. scope, procedures, practice and quality
- C. policies, procedures, practice and environment
- D. policies, procedures, practice and proof
Answer: D
NEW QUESTION # 259
......
Updated Verified CPIM dumps Q&As - Pass Guarantee or Full Refund: https://examsforall.lead2passexam.com/APICS/valid-CPIM-exam-dumps.html